Kwinana Freeway Northbound Widening

  • Widening the freeway from Russell Road to Roe Highway
  • Construction commenced in 2018 and is expected to be completed in late-2019
  • Reduce travel times and ease congestion

Overview

This project forms part of our overall plan to transform Mitchell and Kwinana freeways to support population growth and economic development. It involves widening Kwinana Freeway, providing an additional lane between Russell Road and Berrigan Drive and two additional lanes from Berrigan Drive to Farrington Road.

Other works include:

  • Construction of noise walls where required along the western side of Kwinana Freeway
  • Upgrade and realignment of the existing Principal Shared Path (PSP)
  • Modifications to drainage, kerbing, surfacing, lighting, road safety barriers, service relocations, signage and line marking

Related works in the area:

  • Construction of Collector Distributor (CD) roads associated with the Armadale Road to North Lake Road Bridge project. CD roads are lower speed roads parallel to the freeway to provide merging opportunities.
  • Construction of a fourth lane along Kwinana Freeway from the CD road on-ramp to the freight rail line.

Project Update

PSP detour update

The fifth phase of cyclist and pedestrian detours will begin in the coming days with changes at the northern and southern ends of the works. Please see our latest update for more information.

Upgrade and closure of PSP access points

The existing Principal Shared Path between Russell Road and Farrington Road is being realigned to provide space for the additional northbound freeway lanes. Twelve access points are being upgraded as part of works. Eight existing access points cannot be upgraded to meet the new standard and will permanently close.

Read our latest project update to find out more about the recent Kwinana Freeway beam lifts, the status of construction and some of the sustainability initiatives that form part of this important project.

Cyclist and pedestrian detours

A series of detours are in place to ensure the safety of cyclists, pedestrians, road users and our workforce. See the detour maps for more information.

Timeline

  • May 2018: Contract awarded
  • Mid to late 2018: Construction commenced
  • Late 2019: Construction due for completion

 

 

Image: Kwinana Freeway Northbound Widening map

Benefits

​Funding

The State and Commonwealth Governments have committed $49 million, as part of a $2.3 billion package of road and rail infrastructure works.

​Find out more

Online Survey  - How effectively are we engaging with you?

Major Road and Rail Projects in Perth's Southern Corridor - August 2018

Fact Sheet - May 2017

Principal Shared Path Detours

Phase 5 - Detour information - from late June 2019 

Phase 4 - Detour information - from 21 January 2019

Phase 3 - Detour Information and Frequently Asked Questions - from 10 December 2018

Project update

Upgrade and closure of PSP access points - May 2019

May 2019

September 2018

April 2018

August 2017

Information Sheets

Vibration

Dust

Night Works

Environment

Property Surveys 

Construction Reference Group

Meeting minutes - March 2019 

Meeting minutes - July 2018

Media Statements

Perth's big job-creating road build making huge progress - 3 July 2019

Overhaul of Mitchell and Kwinana freeways begin - 14 October 2018

Perth's southern suburbs job creating, congestion tackling combo fix - 22 June 2018

Last Updated: 04 July 2019